project simple "Simple Project" "1.0" 2005-06-06 - 2005-06-26 {
currency "USD"
}
account project_cost "Project Costs" cost
account payments "Customer Payments" revenue {
credit 2005-06-08 "Customer down payment" 500.0
}
resource tux "Tux" {
rate 300
}
task items "Project breakdown" {
start 2005-06-06
# The default account for all tasks
account project_cost
task plan "Plan work" {
# Some upfront material cost
startcredit 500.0
length 3d
}
task implementation "Implement work" {
effort 5d
allocate tux
depends !plan
}
task acceptance "Customer acceptance" {
duration 5d
depends !implementation
account payments
# Customer pays at end of acceptance
endcredit 2000.0
}
}
htmlaccountreport "PAndL.html" {
timeformat "%d-%M-%y"
accumulate
columns index, name, weekly
}