responsible <resource>

responsible <resource>
Description

The ID of the resource that is responsible for this task. This value is for documentation purposes only. It's not used by the scheduler.

AttributesNameTypeDescription
resourceID 
Contexttask,
InheritableYesScenario Spec.No
See alsoresource

project prj "Responsible Demo" "1.0" 2005-07-15 - 2005-08-01

resource tux "Tux"
resource ubertux "Uber Tux"

task someJob "Some Job" {
  start 2005-07-15
  effort 1w
  allocate tux
  responsible ubertux
}

taskreport "Job List" {
  columns effort, resources, responsible
}